1) A man completes 5/8 of a job in 10 days. At this rate, how many more days will it takes him to finish the job?
  • A)

  • B)

  • C)

  • D)

  • E)

Next
Show Answer:
Show Answer


More Question
A wheel that has 6 cogs is meshed with a larger wheel of 14 cogs. When the smaller wheel has made 21 revolutions, then the number of revolutions mad by the larger wheel is:
3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day
36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work
If the cost of x metres of wire is d rupees, then what is the cost (in rupees) of y metres of wire at the same rate
39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, working 6 hours a day, complete the work